In a construction project:
- Planned Value (PV): $100,000
- Earned Value (EV): $80,000
- Actual Cost (AC): $90,000
Analysis:
- CPI: $80,000 / $90,000 = 0.89 (indicating a cost overrun)
- SPI: $80,000 / $100,000 = 0.8 (indicating a schedule delay)
This analysis helps the project manager identify inefficiencies and implement corrective measures.